Brooklyn Bridge Repairs Running High
Back in 2010 the original estimated cost for the much needed repairs to the 133-year-old Brooklyn Bridge was put at about $508 million. In 2015 the bill was then set to reach about $600 million.
Now New Yorkers can expect to pay in the vicinity of $811 million. That is an almost 60 percent increase over the original cost estimate.
The steep increase in cost is blamed on “scope changes” and “unforeseen field conditions.” And not only will it be costlier to build than originally expected, the probable completion date has been moved back to April 2017. That is four years later than the original plan called for.
“Big public projects take too long to complete and routinely run over budget,” said Maria Doulis, from the Citizens Budget Commission, a watchdog group.
“The city has made attempts to be more transparent about this by posting information online, but it’s unclear what actions are being taken to evaluate and address the root causes.”
New Yorkers will be footing 54 percent of the cost, while the federal government will pick up the rest of the tab. The Department of Transportation said the additional work will include steel repairs, painting of more areas of the bridge, and even fixing damage that was caused to protective shielding which occurred as a result of a barge accident.